This Annex describes the methods and input data used for the estimation of the Levelised Cost of Hydrogen (LCOH) that was presented in Chapter 2. LCOH corresponds to the overall production cost of the hydrogen produced over the lifespan of the investment which depends on CAPEX and OPEX.
Implementing the OECD Framework for Industry’s Net‑Zero Transition in Egypt
Annex A. Methodology and input data
Copy link to Annex A. Methodology and input dataMethodology
Copy link to MethodologyGreen hydrogen
For the green hydrogen production system, the model is structured within an optimisation framework that determines the optimal sizes of system components and their operation schedule, aiming to minimise the LCOH while ensuring a constant hourly hydrogen output throughout the year. This objective is formulated as a mixed-integer linear programming (MILP) optimisation problem. A cost-optimisation algorithm is implemented in MATLAB and solved using the Gurobi™ solver.
The model simulates system operations over an entire year with hourly time resolution. Hourly PV and wind electricity generation profiles are based on historical data for the selected plant location, representing a typical year. For each hourly time step, the equations governing the behaviour of each system component are solved, determining the energy flows entering and exiting each component. The full set of techno‑economic assumptions is detailed in Tables A A.1., A A.2. and A A.3.
Specific technological assumptions were discussed in Chapter 2 to produce 100 kt H2 per year with a constant hourly demand all year round (11 414 t H2/h). Regarding storage, both Li-ion BESS and hydrogen storage in pressurised vessels are considered for short-duration balancing to minimise the oversizing of the renewable power generation plant. The storage system sizes are determined by the optimisation algorithm to minimise the LCOH while ensuring the hourly hydrogen demand is met. Given the seasonal stability of renewable power generation Figure A A.1), seasonal hydrogen storage in salt caverns is not considered. For both storage systems, non-negative annual balances are imposed to ensure that the stored amount at the end of the simulated year matches the initial amount, enabling identical performance in subsequent years and ensuring multi-year plant operation.
Figure A A.1. Duration curves for wind and solar power generation for Suez area in 2019
Copy link to Figure A A.1. Duration curves for wind and solar power generation for Suez area in 2019Blue hydrogen
For blue hydrogen production, two technologies (SMR and ATR) are evaluated by developing models using Aspen Plus process simulation software to work under steady state conditions. A third technological option for blue hydrogen production would be the SMR with a CO2 separation section from the syngas flow. This is more complex to be implemented as a retrofit solution and yields lower overall carbon capture reduction (in the range 60-70% of the total inlet C). Hence, this configuration is not further discussed.
Input data
Copy link to Input dataThe calculation of the LCOH needs input data as following: (i) economic data about technology investment and operation costs; (ii) cost of commodities; (iii) technical data about performances of technologies (i.e. efficiencies, lifetime); (iv) location-specific availability of the renewable sources (wind and solar).
Economic and technical data
Economic data including capital investment and O&M costs for the components of the hydrogen production systems were obtained from the relevant sources recently published. Fixed O&M for each component is considered as a percentage of the original investment cost. Natural gas, desalinated water and grid electricity costs are considered constant values equivalent to the current prices in Egypt. A 10% discount rate is assumed for the analysis.
Investment and fixed O&M costs are expected to decrease over time due to greater technology adoption and economies of scale. To account for this, two cost scenarios are considered for LCOH estimation: the base case, which reflects current technology costs, and the future scenario, which incorporates projected cost reductions. To address uncertainties in battery storage and ammonia cracking costs, two CAPEX values are used. For BESS, a low estimate of USD 200/kWhel and a high estimate of USD 400/kWhel are considered. For the ammonia cracking plant, CAPEX values of USD 1.42 M /MWNH3nom and USD 2.24M / MWNH3nom are based on recent studies.
The renewable energy efficiencies are embedded in hourly generation profiles. Battery storage has a charge/discharge efficiency of 90% (81% round-trip efficiency) and a 4-hour energy-to-power ratio. Electrolyser efficiency is based on recent studies (UNIDO, 2023[2]). Hydrogen storage assumes no leakage in pressurised tanks. Electricity transmission losses are 3.5% per 1 000 km for HVDC cables and 1.5% for AC/DC and DC/AC conversions. Hydrogen transport pipelines assume a 0.1% loss per 1 000 km and an energy use of 0.027 kWhe/km/kg H2.
For the blue hydrogen simulations, the economic analysis follows a bottom-up approach, where capital costs for each installed component are estimated using cost functions. All costs are adjusted to the reference year 2023 using the Chemical Engineering Plant Cost Index (CEPCI), with a 2023 index value of 797.6.
The values used in the herein presented work are summarised in Table A A.1, Table A A.2 and Table A A.3. References for the selected values are included in each table.
Table A A.1. Green hydrogen production, techno-economic assumptions
Copy link to Table A A.1. Green hydrogen production, techno-economic assumptions|
Components |
CAPEX |
CAPEX reference values |
OPEX |
Performance parameters |
|
|---|---|---|---|---|---|
|
Base case |
Future |
||||
|
PV power generation plant |
USD 600 /kWnom |
USD 350 /kWnom |
(IRENA, 2022[3]): USD 876/kWnom in 2022; USD 707/kWnom in 2030 via power law regression of historical data. (LUT, n.d.[4]): Optimally tilted PV: USD 432/kWnom in 2020; USD 278/kWnom in 2030 (may scale x2 compared with historical IRENA data). (IRENA, 2019[5]): USD 340-834/kWnom in 2030 (with an avg. of USD 587/kWnom). |
2%/y of CAPEX |
Profile = f(location) Lifetime = 25 years |
|
Onshore wind power generation plant |
USD 1 100 /kWnom |
USD 1 100 /kWnom |
(IRENA, 2022[3]): Global average: USD 1 274/kWnom in 2022; African average: USD 1 685/kWnom in 2022. (LUT, n.d.[4]) : 1 000 USD/kWnom |
2%/y of CAPEX |
Profile = f(location) Lifetime = 30 years |
|
Battery Energy Storage System (BESS) |
USD 200-400 /kWhe |
USD 175/kWhe |
(IEA, 2023[6]): USD 290/kWhe in 2023; USD 175/kWhe in 2030. |
2%/y of CAPEX |
ηcharge = 0.9 - ηdischarge = 0.9 Self-discharge = 3%/month Lifetime = 20 years Replacement cost = 60% initial CAPEX (at year 10) Energy/Power ratio =4 kWh/kW |
|
Low-temperature electrolysis system |
USD 800 /kWnom |
USD 400 /kWnom |
(IRENA, 2020[7]): USD 500-1000/kWe, with avg. range @100MWmodules of USD 400-500/kWe in 2020. (LUT, n.d.[4]): USD 685/kWe in 2020; USD 363/kWe in 2030. (IRENA, n.d.[8]): USD 540/kWe in 2030. |
3%/y of CAPEX |
η = 0.6 (55.56 kWhe /kgH2) Min. load fraction = 20% Lifetime = 20 years Replacement cost = 40% initial CAPEX (at year 10) |
|
Hydrogen compressors |
USD 1 600 /kWhe |
(Crespi et al., 2021[9]): EUR 1 600 /kWe. Compressor has very small impact on the analysis. |
1%/y of CAPEX |
ηcompressor = 0.63 Delivery pressure = 220 bar Lifetime = 25 years |
|
|
Electricity transmission line (overhead cables) |
HVDC USD 300 /GW/m |
JRC Technical Report, HVDC submarine power cables in the world (Ardelean, 2015[10]) |
1%/y of CAPEX |
HVDC Power Loss = 3.5% EEtrans/1 000 km AC/DC & DC/AC converters loss = 1.5% EEconv Lifetime = 40 years |
|
|
H2 storage |
USD 500 USD/kg H |
US DOE targets (DOE, n.d.[11]): USD 450/kgH2 (160 bar); USD 600/kgH2 (high pressure). FCHJU 2020-2030 targets (Clean Hydrogen Partnership, n.d.[12]): EUR 350/kg H2 |
4%/y of CAPEX |
Negligible leakage Lifetime = 30 years |
|
|
H2 transport pipelines |
USD 0.988/km/kWLHV H2 |
5%/y of CAPEX |
Loss = 0.1%/1000 km |
||
|
Grid electricity |
(EgyptERA, 2024[14]) Energy Cost: USD 21 /MWh - Grid fees: USD 0.65 /MWh |
||||
|
Desalination |
UNIDO-POLIMI recent work: Levelized cost of demi inlet water: USD 0.01/kgH2 |
||||
|
Others |
Discount rate = 10% |
||||
Table A A.2. Blue hydrogen production, techno-economic assumptions
Copy link to Table A A.2. Blue hydrogen production, techno-economic assumptions|
Steam reforming with carbon capture |
|||||
|---|---|---|---|---|---|
|
Category |
Parameter |
Unit |
Reference size |
Reference cost 2023 [M USD] |
Scaling exponent |
|
Pre-reformer (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
Natural gas flow rate |
[kg/s] |
17.7 |
4.6 |
0.67 |
|
Sulphur guard bed (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
Natural gas flow rate |
[kg/s] |
17.7 |
2.2 |
0.67 |
|
Syngas coolers (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
Syngas flow rate |
[kg/s] |
67.4 |
25.6 |
0.67 |
|
Cooling water system (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
H2 flow rate |
[kg/s] |
5.6 |
51.1 |
0.67 |
|
Fired tubular reformer (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
Syngas flow rate |
[kg/s] |
67.4 |
85.6 |
0.67 |
|
Furnace air blower (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
Air flow rate |
[kg/s] |
165 |
5.5 |
0.67 |
|
Water gas shift reactor (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
Syngas flow rate |
[kg/s] |
67.4 |
16.8 |
0.67 |
|
MEA CO2 capture plant (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
CO2 flowrate |
[kg/s] |
22.2 |
98.3 |
0.67 |
|
CO2 compression and drying (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
CO2 flowrate |
[kg/s] |
55.5 |
93.3 |
0.67 |
|
CO2 compression aftercoolers (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
CO2 flowrate |
[kg/s] |
55.5 |
6.4 |
0.67 |
|
Pressure Swing Adsorber (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
H2 flow rate |
[kg/s] |
5.6 |
34.0 |
0.67 |
|
Hydrogen compressor (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
H2 flow rate |
[kg/s] |
5.6 |
15.4 |
0.67 |
|
Feedwater and miscellaneous BOP systems |
H2 flow rate |
[kg/s] |
5.6 |
196.3 |
0.67 |
|
Autothermal reforming with carbon capture |
|||||
|
Air separation unit (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
O2 flow rate |
[kg/s] |
35.5 |
216.9 |
0.5 |
|
Autothermal reformer (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
Syngas flow rate |
[kg/s] |
72.2 |
13.9 |
0.67 |
|
PSA off gas boiler, ductwork and stack (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
Exhausts flow rate |
[kg/s] |
45.1 |
20.2 |
0.67 |
|
MDEA CO2 capture plant (de Cataldo et al., 2024[15]; IEAGHG, 2017[16]) |
CO2 flowrate |
[kg/s] |
34.8 |
48.2 |
0.67 |
|
Natural gas (GASREG, 2024[17]) |
4.85 |
USD /GJLHV |
Grid electricity (EgyptERA, 2024[14]) |
21 |
USD/MWh |
|
CO2 storage cost |
10 |
USD /tCO2 |
Levelised cost of desalinated water |
0.01 |
USD/kgH2 |
|
CAPEX of CO2 transport (1) New pipeline (EgyptERA, 2024[14]) (2) Retrofitted pipeline (EgyptERA, 2024[14]) |
(1) 1.21 (2) 0.3 |
USD bn/ 1000 km |
CO2 storage cost |
10 |
USD/tCO2 |
|
OPEX-CO2 transport |
0.05 |
USD /kgCO2/1000 km |
CO2 emission tax |
0 |
USD/tCO2 |
|
Construction period |
3 |
years |
Construction period |
3 |
Years |
|
Plant lifetime |
25 |
years |
Plant lifetime |
25 |
Years |
|
Discount rate |
10 |
% |
Capital expenditure curve |
20/45/35% |
First/second/third year) |
|
Average salary |
30 000 |
USD /year |
Capacity factor |
91% |
8 000 eq. hours/year |
|
Discount rate |
10% |
Inflation rate |
2% |
Owner’s cost |
7% |
|
Average salary |
USD 30 000 /year |
Annual O&M |
1.5% of CAPEX |
Annual insurance and taxes |
1% of CAPEX |
Table A A.3. Ammonia-related systems, techno-economic assumptions
Copy link to Table A A.3. Ammonia-related systems, techno-economic assumptions|
Category |
CAPEX |
CAPEX Reference values |
OPEX |
Performance parameters |
|---|---|---|---|---|
|
Ammonia synthesis (from N2 and H2) |
1.72 |
MUSD/MWNH3nom |
Hank et al. (Hank et al., 2020[18])] |
5% /y of CAPEX |
|
NH3 storage |
810 |
USD/tNH3 |
Nayak-Luke et al. (R.M. Nayak-Luke, 2021[19]) |
3% /y of CAPEX |
|
Ammonia cracking |
1.42 – 2.24 |
M USD/MWNH3nom |
Values herein reported are from (de Cataldo et al., 2024[15]) In (Yun et al., 2024[20]), CAPEX of 0.92 M USD/MWNH3nom is estimated for a plant size of 35 ktNH3/y. In (Devkota et al., 2024[21]), CAPEX of 2.69 M USD/MWNH3nom is estimated for a plant size of 1 ktNH3/y. |
5% /y of CAPEX |
|
N2 cost |
50 |
References
[10] Ardelean, M. (2015), HVDC submarine power cables in the world – State-of-the-art knowledge, Publications Office 2015, Joint Research Centre: Institute for Energy and Transport,.
[12] Clean Hydrogen Partnership (n.d.), FCH 2 JU - MAWP Key Performance Indicators (KPIs).
[9] Crespi, E. et al. (2021), “Design of hybrid power-to-power systems for continuous clean PV-based energy supply”, International Journal of Hydrogen Energy, Vol. 46/26, pp. 13691-13708, https://doi.org/10.1016/j.ijhydene.2020.09.152.
[15] de Cataldo, A. et al. (2024), “Ultra-low emission flexible plants for blue hydrogen and power production, with electrically assisted reformers”, International Journal of Hydrogen Energy, Vol. 49, pp. 978-993, https://doi.org/10.1016/j.ijhydene.2023.10.159.
[21] Devkota, S. et al. (2024), “Techno-economic and environmental assessment of hydrogen production through ammonia decomposition”, Applied Energy, Vol. 358, p. 122605, https://doi.org/10.1016/j.apenergy.2023.122605.
[11] DOE (n.d.), DOE technical targets hydrogen delivery.
[14] EgyptERA (2024), Tariff 2023.
[13] Galimova, T. et al. (2023), “Impact of international transportation chains on cost of green e-hydrogen: Global cost of hydrogen and consequences for Germany and Finland”, Applied Energy, Vol. 347, p. 121369, https://doi.org/10.1016/j.apenergy.2023.121369.
[17] GASREG (2024), Natural Gas Pricing.
[18] Hank, C. et al. (2020), “Energy efficiency and economic assessment of imported energy carriers based on renewable electricity”, Sustainable Energy & Fuels, Vol. 4/5, pp. 2256-2273, https://doi.org/10.1039/d0se00067a.
[6] IEA (2023), World Energy Outlook 2023.
[16] IEAGHG (2017), Reference data and Supporting Literature Reviews for SMR Based Hydrogen Production with CCS, 2017-TR3.
[3] IRENA (2022), Renewable Power Generation Costs in 2022.
[7] IRENA (2020), Green hydrogen cost reduction.
[5] IRENA (2019), Future of Solar Photovoltaic.
[8] IRENA (n.d.), Global Renewables Outlook 2023.
[4] LUT (n.d.), Powerfuels in a Renewable Energy World: Global Volumes, Costs, and Trading 2030 to 2050.
[1] Ninja Renewables (2025), Ninja Renewables, https://www.renewables.ninja/.
[19] R.M. Nayak-Luke, E. (2021), Techno-Economic Challenges of Green Ammonia as an Energy Vector, Elsevier.
[2] UNIDO (2023), Assessment of low carbon hydrogen production, demand, business models and value chain in Egypt, https://www.unido.org/sites/default/files/files/2023-06/Low-Carbon-Hydrogen-Assessments-in-Egypt-Highlights-UNIDO.pdf.
[20] Yun, S. et al. (2024), “Enhanced ammonia-cracking process via induction heating for green hydrogen: A comprehensive energy, exergy, economic, and environmental (4E) analysis”, Chemical Engineering Journal, Vol. 491, p. 151875, https://doi.org/10.1016/j.cej.2024.151875.
[22] Zhang, H. et al. (2020), “Techno-economic comparison of green ammonia production processes”, Applied Energy, Vol. 259, p. 114135, https://doi.org/10.1016/j.apenergy.2019.114135.