1. Grid Capacity Title (reserva de capacidade de injeção) in the Portuguese Electricity System (RESP), grants grid access rights at a specified substation and voltage level. This can be obtained through:
General Access – requested directly to DGEG , if grid capacity is publicly available;
Agreement with the Grid Operator, where the promoter co-finances grid expansion;
Tender Procedures, organised by the government for capacity allocation.
2. Environmental clearance: evaluated by APA or CCDRs depending on project location and size; either:
A DIA (Declaração de Impacte Ambiental or Environmental Impact Statement), if they exceed 50 MW or affect sensitive areas; or
A DINCA (Declaração de Incidências Ambientais or Simplified Environmental Impact Assessment) for projects in protected zones.
3. Production license: issued by DGEG and requires a financial deposit (EUR 10,000/MVA). The application must be submitted within:
4. Municipal Construction Approval: mandatory for all PV projects, as solar plants qualify as “urbanistic operations”. The process includes assessment of land-use compatibility and consultation with external authorities.
5. Gird connection. the promoter must build and secure infrastructure, validate it through the DSO E-Redes or the TSO REN, depending on whether it is less than or more than 50 MVA. Connection is subject to:
Technical validation by the grid operator (E-Redes or REN);
Securing land rights or easements;
Providing performance guarantees.
6. Municipal Compensation Protocol. If the project has a capacity over 50 MVA, the developer must provide one of the following:
a small self-consumption unit (UPAC), a storage facility for installation in municipal buildings or collective use equipment, and EV chargers for public use with an equivalent capacity; or
a financial compensation of EUR 1 500/MVA.
This agreement must be formalised in a protocol with the municipality and is a condition for receiving the final license.
7. Operation License – issued by DGEG once the plant meets with technical, environmental, and legal requirements. While projects can start operating early under exceptional measures, a formal license must be obtained within three years.
The Environmental Impact Assessment (EIA) regime in Portugal is governed by Decree-Law No. 151-B/2013. This has been amended, most recently by Decree-Law No. 11/2023 of 10 February, under the "Environmental SIMPLEX" (SIMPLEX Ambiental) (Servulo & Associados, 2023[6]). This reform included reduction in the number of projects subject to mandatory EIA, streamlined procedures, and introduced tacit approval mechanisms.
The revised regime narrows the use of case-by-case screenings and further limits mandatory EIA requirements. Case-by-case assessments are now reserved for projects located outside sensitive areas that do not meet established thresholds or fall under specific exceptions. The list of projects subject to mandatory EIA has been further reduced. For example, in addition to the longstanding exemption for projects with an installed capacity of less than 50 MW, EIA is no longer mandatory for PV solar projects occupying less than 100 hectares (or for wind farms comprising fewer than 20 turbines (or fewer than 10 turbines if located in sensitive areas)).20
Decree-Law No. 99/2024 introduced additional modifications to the EIA legal framework. Modifications included, amongst others, a requirement for renewable energy production facilities subject to an EIA to submit a proposal defining the scope of the EIA and exemptions from the EIA process for rooftop installations, installations on artificial surfaces, and repowering of existing projects.21
Where an EIA is required, the APA co-ordinates the evaluation process. A key part of this process is the formation of an Evaluation Commission (Comissão de Avaliação).22 This Commission is an inter-institutional commission convened by the APA to assess the environmental and territorial impacts of projects subject to EIA. Its role is to evaluate the Environmental Impact Study (EIS) submitted by the developer and issue a co-ordinated opinion that will inform the final Environmental Impact Statement (DIA). It plays a decisive role in whether and how a project moves forward.
Key tasks of the Commission include (APREN, 2023[7]):
Analysis of the Environmental Impact Study (EIS), assess its completeness, scientific quality, and relevance of the analysis.
Review of impacts on land-use, biodiversity, water, landscape, noise, etc.
a) Request Clarifications or Additional Information
b) Propose Mitigation or Compensation Measures
c) Issue a Joint Technical Opinion
d) Inform the Public Consultation
Commission membership varies depending on project characteristics. These include the nature, location, and potential impacts of the project. The APA coordinates an also includes23 DGEG, CCDR Algarve, ICNF (Institute for Nature and Forest Conservation) – if protected species or areas are affected, Municipalities – especially those directly affected by the project, Regional Health Authorities – if public health concerns are relevant, Cultural Heritage Authorities – if archaeological or heritage sites are involved, INAG or ARH – for water resource management.
Additional institutions may be invited depending on the project’s scope (e.g. maritime authorities, geological agency). Although municipalities are formally part of the commission, stakeholders have reported cases where they are excluded in practice, limiting local input during the environmental assessment, wit possible implications further in the permitting phase.